I've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete.
Is there a setting I need to change to make sure these two columns show the same data?
thanks
I've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete.
Is there a setting I need to change to make sure these two columns show the same data?
thanks
The activity performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.
You can set the performance percent complete under WBS module. See below:
Tools
Admin Preferences
Earned Value Tab
Make sure that the Technique for computing performance percent complete is set to
Activity % Complete
and that Earned value calculation is set to Budgeted Values with current date is at the bottom of this same tab.
Also at the Project levele under Setings make sure that Baseline for earned value calculatons is set to Project Baseline
It is at the WBS level, the Earned Value tab.