Performance % Complete

E
Emma Lang 👤 Member for 9 years 9 months

I've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete. 

Is there a setting I need to change to make sure these two columns show the same data?

 

thanks

R
Rodel Marasigan 👤 Member for 19 years 7 months

The activity performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

You can set the performance percent complete under WBS module. See below:

Performance-percent-Complete

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Tools

Admin Preferences

Earned Value Tab

Make sure that the Technique for computing performance percent complete is set to

Activity % Complete

and that Earned value calculation is set to Budgeted Values with current date is at the bottom of this same tab.

Also at the Project levele under Setings make sure that Baseline for earned value calculatons is  set to Project Baseline

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts