Helo All,
What error am I doing.
The below pic shows the duration of the activity and WBS
WBS Total570PrimaveraStart Finish Activity A13-Apr-2329-May-2330Activity B30-May-232-Aug-242954Activity C3-Aug-2416-Sep-2445
But the same thing if I put it in excel gives me this duration.
ExcelStart Finish Activity A13-Apr-2329-May-2347Activity B30-May-232-Aug-24431Activity C3-Aug-2416-Sep-2445 Excel Total523
I would like to show the excel duration in the schedule
The calendar for 1st activity = 8 Hrs X 5 Days and the other 2 activity = 8 Hrs X 7 Days
Please guide me.
Thanks
Jithin
because the schedule is based on 8 hours per day based on the calendar
excel does not consider TIMES it is just a day for day calculation
P6 uses times in the background
Hi All,
The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table.
So why is it like that?