Doubt in Duration

Helo All,

What error am I doing.

 

The below pic shows the duration of the activity and WBS

  WBS Total570PrimaveraStart Finish Activity A13-Apr-2329-May-2330Activity B30-May-232-Aug-242954Activity C3-Aug-2416-Sep-2445

 

But the same thing if I put it in excel gives me this duration.

ExcelStart Finish Activity A13-Apr-2329-May-2347Activity B30-May-232-Aug-24431Activity C3-Aug-2416-Sep-2445  Excel Total523

I would like to show the excel duration in the schedule 

 

The calendar for 1st activity = 8 Hrs X 5 Days and the other 2 activity = 8 Hrs X 7 Days

Image removed.

Please guide me.

 

Thanks 

Jithin

Z
Zoltan Palffy 👤 Member for 16 years 10 months

because the schedule is based on 8 hours per day based on the calendar

excel does not consider TIMES it is just a day for day calculation

P6 uses times in the background

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi All,

 

The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table.

 

So why is it like that?

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts