Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do? - because it is true, it does not make sense. I assume people copy the dates to a column and delete them in the udf column - but sounds like a huge hassle - is there an easier way? is this something Oracle should fix - I guess I always just ignored it.
Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
if an activty is complete it still has an original late date even thought this is no longer part of the total float calculations. However if activities are in progress its has a remaining late finsh date. For activites that are COMPLETED there is not and Remaining Late Finish date so it might be best to show the remaining late finish date column.
If the activity is complete there is no remaining late date. If the activity is in progress with float then it has remaining late dates.