Primavera P6 Solves the Start-to-Start Open Network Problem
Forum TopicHere's how Primavera P6 helps solve the Start-to-Start open network problem http://ow.ly/Ddrlv
Here's how Primavera P6 helps solve the Start-to-Start open network problem http://ow.ly/Ddrlv
Hi, I have been struggling with this problem for some time now and have not managed to resolve it.It is a fairly large program so it would be useful to find the solution to my problem.I usually review the activities and update each one with the repor...
I am new to the Offshore field, Project allotted me is Buoy where i need to develop the construction and Pre commissioning and Commissioning Activity.. If any one have the Buoy schedule Plz share with me on [email protected],Udaya
Please anyone can help me about ...how to get a report in P6 showing Number of activities done per month along the project duration ? thnx
Hello Experts I am struggling with the below scenario and hope one of you can help me out. I have some plans working on a 7day 7 hour calendar. If I have a task which only takes 2 hours to do and lets say 3 men to do it, I want to be able to show in...
I have a schedule with a concrete resource loaded agaianst several hundred activities. The concrete activties have been prioritized using the "Activity Leveling Priority". When viewing the Resource Assignment screen, I used to be able to group by t...
Hi,in P6 I would like to display some project codes in a print layout. The codes I need are not listed in the selection box.Could anybody tell me how this works?Thanks in advance!Best regards,Nico
Hi,Must I use TIA, IAP, APAB, CAB to do EOT claim and evaluation ?If I can prove the delay not using the above method, will it be acceptable ?I'm not using P6 but Microsoft project, all I need is to identify the critical path from the programme and p...
Dear Planners,I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I ha...
Hello guys, I have loaded the manhrs in p6 to my project. The problem which i am facing is my stacked histogram graph peaks does not match my resource histogram peaks.As i sant to have my histogram trade wise.. and its getting complicated . please h...
Hello All,I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout. I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the da...
Hi,We have a sub-con who has loaded Manhours as a resource for all the Disciplines and related activities. As per contract client has specified that 260mhrs/month need to be considered as basis for planning. On this basis they have extracted from P6 ...
Hi,Can anyone please help me with any existing document; and any online locations where I can get details regarding the PMDB database. What I precisely need is to get the name of table/field in PMDB database; for fields in P6 front end.E.g: Project ...
Hello dears,Can anybody provide me the sample of mechanical erection project plan on P3 or P6.Looking for positive response. Regards,
hi everyone, I'm quite sure this question already popped, but I can't really find what I'm looking for. for each of our projects, we need P6 to calculate an actual amount of actual labor units for each task in the project BUT we need to enter a % for...
Here's how to solve the Primavera P6 Professional HMTL Title Block issue http://ow.ly/uxJbG
Would you want to be a planner with a specialised contractor doing multiple projects or general contractor/owner doing one big project ?
I'm learning P6 and having some trouble getting the footers to be unique to each project and folder that I need to update. Especially the revision levels. Each time I update a revision level, it applies itself to every schedule I open after that. ...
Hi,I am a new member of this forum and new to process engineering field. I would like to seek your valued help regarding a project I am currently working on. I would like to know how I can plan and schedule a pipeline replacement project. Any help (W...
Hi folks,Critical path is the sequences of activities which their Total float is 0. When this sequence is defined, it is already late to take countermeasure,I need to determine earlier the sequence of activities which would delay the project finish d...