I'm learning P6 and having some trouble getting the footers to be unique to each project and folder that I need to update. Especially the revision levels. Each time I update a revision level, it applies itself to every schedule I open after that. There must be a way to avoid re-entering all the footer data for each schedule I update.
Thanks in advance.
Try making your layouts, project layout rather than Global