Display Project Codes in Layout

Hi,

in P6 I would like to display some project codes in a print layout. The codes I need are not listed in the selection box.

Could anybody tell me how this works?

Thanks in advance!

Best regards,

Nico

G
Gary Whitehead 👤 Member for 17 years 2 months

Nico,

 

I don't believe you can include project codes in the print layout.

N
Nathaniel Alexander 👤 Member for 14 years 7 months

Hello Nico,

To add project codes you need to do the following.

1) Go to ENTERPRISE

2) Select Project Codes - A pop up box will appear

3) At the top right hand side you need to click on Modify - This will open the Project Definitions Box

4) Add the Project codes that you require- then close the Project Codes Definitions box.

5) On the top left hand side there is a window - Click on the down key, then select the Project Code Definition

6) You can now add any other codes you need. and close box

7) You then go back to ENTERPRISE

8) Select Projects and select the project you want to add the code to

9) In the bottom layout - select codes and asssign

Hope this helps

Nat

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts