Non-Labor Resource Assignment in Columns in a Layout

Hello All,

I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout.  I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?

Thanks

 

Pranab

P
Patricia Le Clainche 👤 Member for 19 years

Dear all,

Did you try in Resources Assignments View ? It should be OK. You can filter for instance by Resource Type =Non Labor. You can add columns dealing with costs. On spreadsheet, you can select costs or units, per period (month, quarter...) or cumulative.

Regards.

Patricia

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hi Schedulers,

Can this not be done? Can we not have a layout with all resource assignment? Has someone designed such a layout?

Thanks,

Pranab

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts