EOT Evaluation

T
Tim Tam 👤 Member for 13 years 1 month

Hi,

Must I use TIA, IAP, APAB, CAB to do EOT claim and evaluation ?

If I can prove the delay not using the above method, will it be acceptable ?

I'm not using P6 but Microsoft project, all I need is to identify the critical path from the programme and put in the actual start and finish date of delay into the activities, it will change the end date of the whole program. the difference from the baseline end date and new date will be the delay impact. to me is as simple as that.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Tim Tam

What you have described is an Impacted as Planned delay analysis.

I have prepared a YES / NO flow chart to assist in the decision of what analysis method to use for delay analysis.

Send me a message with your email and I will forward it to you.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts