Hello Experts I am struggling with the below scenario and hope one of you can help me out.
I have some plans working on a 7day 7 hour calendar. If I have a task which only takes 2 hours to do and lets say 3 men to do it, I want to be able to show in my histogram that I want 3 people of a particular trade that day.
I am trying to either use Primavera to show the results or by exporting them to Excel but the results I am getting only show that I want 1 person because it equates a full day to 7 hours and knows I need to get 6 hours of work done.
Can anyone help please?
David,
In admin preferences set the time period according to your calendar setting.
Make sure the activity calendar is the same as the resource calendar and as well as the default calendar.
Regards,