Search

S Curve re-baseline retrospective comparison

Forum Topic

Dear All, I have re-baselined a percentage complete (earned Man-hour value / budgeted Manhour value)  v/s. Time S - Curve at 75% project completion.Subsequently I have been asked to determine Retrospectively , what was the earned value % when the pro...

Jul 23, 2014

Software for fast "visual" programme

Forum Topic

Good morning everybody!Just a quick question probably for some of you:Is there any free software I can use to create fast and clear small programme with the pourpouse of rapresentation/comparison of programme?I try to explain it better:Sometimes I wo...

Jul 23, 2014

Which of the following webinar topics interest you most?

Forum Topic

Hello,  I represent ISS Art, LLC, a software development compeny. We’re going to organize a free webinar, and we need to define the topic that would be the most interesting. Currently we have the following topics in mind:1.   Time tracking systems2. ...

Jul 24, 2014

Activity Relationships for Level of Effort

Forum Topic

Hello, new guy here.  I've seen several different schedules, by several different schedulers, that have their LOEs with the SS  and FF relationships as predecessors only.  Reading up on all the material I can find nearly everyone says, from P6 docume...

Jul 24, 2014

Cost Loading Using Global Change

Forum Topic

Hi!Can somebody help me how to use global change in cost loading please.Im currently using primavera p6 for my project schedule.Thanks!

Jul 26, 2014

Physical Percentage Progress type and Actual Units

Forum Topic

While using the Physical Percent Complete, the actual units is not getting updated automatically during the progress update(activity % complete). If duration percent complete is used, actual units will be updated automatically.Is there any option to ...

Jul 26, 2014

Unable to assign project code to activities

Forum Topic

Have added a "project" code and when I go to Enterprise/Project Codes it shows up, but cannot find it on the list when I try to assign the code to an activity and have chosen the "Display: All Values."

Jul 27, 2014

How do you communicate schedule and tasks to project team

Forum Topic

Dear all,may be a stupid question, but just wondering: how do you communicate "who is doing what and when" to your project team, when doing schedule in MS Project. I do it in the following way:In Gantt Chard I create view, which I want to use to comm...

Jul 27, 2014

What has happened to PP

Forum Topic

I haven’t been in PP for a while, but was amazed at how little forum questions are asked, used to be one every few minutes and so few jobs, this site used to be buzzing with activities which raises a few questions:Where are all the eastern participan...

Jul 29, 2014

How do you assign weight to the activities

Forum Topic

Hi, i need to specify the weight (incidence, etc) of the activity. Using the resources....a mean work hours...if i have: Proyect Name            10 working hours (summarize)       % of working hours of total- Act 1                      2 working hour...

Jul 30, 2014

Free webinar: An Introduction to EcoSys EPC

Forum Topic

Date: TODAY Thurs, July 31, 2014Session 1: EMEA 14:00 UTC / 15:00 BST / 10am EDTSession 2: Americas 2pm EDT / 11am PDTDuration: 1 hrOrganizations are demanding greater visibility and accountability along with improved performance for their projects. ...

Jul 31, 2014

Bidding Schedule for EPC

Forum Topic

Dear all,Good day! I was asked to draft a bidding schedule for Engineering and Procurement as well as construction management for an H2 project. Can somebody extend their helping hands?Thanks,Wally

Jul 31, 2014

Contractor denies to submit Revised Clause 14.1 Program for 2 YRS

Forum Topic

Dear All,Our Road/Brodges project with Original Duration of 2 yrs costing 5bn UAE Dirhams was started in Jan 2012. Contractor submitted CL14 programme within 28 days from work order.  But the scope of work was keep on inceasing from time to time and ...

Jul 31, 2014

Original Durations incorrect

Forum Topic

Hi, Just wondering if someone can shed some light on a problem that has just popped up. When we open any project in the sytem the orginal durations, (Group Sorted by WBS Levels) for the header is stating less days than it actually is.It is not a user...

Aug 1, 2014

Is Your Primavera P6 Activity Layout Really Corrupt?

Forum Topic

From time to time when working in the Activity View of Primavera P6 Professional, I find that I get Access Violation errors like the one in the screenshot here http://ow.ly/zQqFW I've posted why this occurs and some workarounds.

Aug 1, 2014

Force Majeure

Forum Topic

Dear All, If a project is suspended for a period more than 60 days due to an accident ,whether the incident comes under Force majeure since its beyond partys control Regards SV

Aug 4, 2014