Dear all,
Good day! I was asked to draft a bidding schedule for Engineering and Procurement as well as construction management for an H2 project. Can somebody extend their helping hands?
Thanks,
Wally
Dear all,
Good day! I was asked to draft a bidding schedule for Engineering and Procurement as well as construction management for an H2 project. Can somebody extend their helping hands?
Thanks,
Wally
Hi Mike, Thanks. Been trying to delete the 2 posts but cannot find the option. I've been given the duration already for the aforementioned tasks. What I'm after are the processes/activities involved in EPC bidding. Do you have sample schedule either in p6 or MS project that I can refer?
If in case, can you kindly email at this id? [email protected]
Regards,
Wally
Hi Wally - welcome to planning planet - next time only hit the "save" button once.
The basic principle of a bid tender is to see if the work can be completed in the stated contract period.
Do not try to squeeze durations to make it fit - that is for the bid manager to decide after he has all the facts.
So make sure your durations and logic is correct - particularly with the Engineering / Procurement sections.
Work at level 4 with FS links.
Make sure that the Employer's deliverables are set with clear milestones linked ALAP to the Contractor's task.
Best regards
Mike Testro