How do you assign weight to the activities

Hi, i need to specify the weight (incidence, etc) of the activity. Using the resources....a mean work hours...

if i have:

 

Proyect Name            10 working hours (summarize)       % of working hours of total

- Act 1                      2 working hours                             20%

- Act 2                      2 wh                                            20%

- Act 3                      2 wh                                            20%

- Act 4                      4 wh                                            40%

 

how do you show this percent? .... do you have to create?? how do you create?? .... (sorry my english), hope you can helpme

 

Bye!

M
Mike Testro 👤 Member for 20 years 7 months

Hi Claudio

Welcome to Planning Planet.

You will never have to apply weighting again if you set your programme at level 4 with each task representing one trade in one location.

Best regards

Mike Testro

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts