How do you assign weight to the activities

Hi, i need to specify the weight (incidence, etc) of the activity. Using the resources....a mean work hours...

if i have:

 

Proyect Name            10 working hours (summarize)       % of working hours of total

- Act 1                      2 working hours                             20%

- Act 2                      2 wh                                            20%

- Act 3                      2 wh                                            20%

- Act 4                      4 wh                                            40%

 

how do you show this percent? .... do you have to create?? how do you create?? .... (sorry my english), hope you can helpme

 

Bye!

M
Mike Testro 👤 Member for 20 years 5 months

Hi Claudio

Welcome to Planning Planet.

You will never have to apply weighting again if you set your programme at level 4 with each task representing one trade in one location.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts