How to equal actual labor units to earned value labor units in Primavera P6

Hi all,

I'm trying to make the actual labor units equal to the earned value labor units. I would like to do this either by global change or through export/import (excel).

I know I can do it manually, but that costs a lot of time. And I do understand, that once you press F9 it's all lost, so that why I want to do it through automated actions.

I have tried a few global changes, but it either ends in all errors or in all zero's. So please provide a step by step procedure.

I want to do this, so I can forecast how many units (hours) we need per week to complete the schedule. Where I would use the resource assignment calendar from Primavera.

Best regards,

Anton Broekzitter

S
Shaohua Chen 👤 Member for 8 years 5 months

when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .

S
Shaohua Chen 👤 Member for 8 years 5 months

when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .

S
Shaohua Chen 👤 Member for 8 years 5 months

when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts