Search

EOT Evaluation

Forum Topic

Hi,Must I use TIA, IAP, APAB, CAB to do EOT claim and evaluation ?If I can prove the delay not using the above method, will it be acceptable ?I'm not using P6 but Microsoft project, all I need is to identify the critical path from the programme and p...

Mar 11, 2014

Hours per TIME pERIOD

Forum Topic

Dear Planners,I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I ha...

Mar 11, 2014

stacked histogram

Forum Topic

Hello guys,  I have loaded the manhrs in p6 to my project. The problem which i am facing is my stacked histogram graph peaks does not match my resource histogram peaks.As i sant to have my histogram trade wise.. and its getting complicated . please h...

Mar 12, 2014

Non-Labor Resource Assignment in Columns in a Layout

Forum Topic

Hello All,I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout.  I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the da...

Mar 12, 2014

Manhours as resource

Forum Topic

Hi,We have a sub-con who has loaded Manhours as a resource for all the Disciplines and related activities. As per contract client has specified that 260mhrs/month need to be considered as basis for planning. On this basis they have extracted from P6 ...

Mar 12, 2014

P6 8.2 PMDB Databse

Forum Topic

Hi,Can anyone please help me with any existing document; and any online locations where I can get details regarding the PMDB database. What I precisely need is to get the name of table/field in PMDB database; for fields in P6 front end.E.g:  Project ...

Mar 13, 2014

Mechanical erection project plan

Forum Topic

Hello dears,Can anybody provide me the sample of mechanical erection project plan on P3 or P6.Looking for positive response. Regards,

Mar 13, 2014

labor units "at complete" not increasing ?

Forum Topic

hi everyone, I'm quite sure this question already popped, but I can't really find what I'm looking for. for each of our projects, we need P6 to calculate an actual amount of actual labor units for each task in the project BUT we need to enter a % for...

Mar 13, 2014

P6 Schedule footer - How to make footer unique to folder

Forum Topic

I'm learning P6 and having some trouble getting the footers to be unique to each project and folder that I need to update.  Especially the revision levels.  Each time I update a revision level, it applies itself to every schedule I open after that.  ...

Mar 13, 2014

A Pipeline Project

Forum Topic

Hi,I am a new member of this forum and new to process engineering field. I would like to seek your valued help regarding a project I am currently working on. I would like to know how I can plan and schedule a pipeline replacement project. Any help (W...

Mar 13, 2014

"critical path" early warning , Total float

Forum Topic

Hi folks,Critical path is the sequences of activities which their Total float is 0. When this sequence is defined, it is already late to take countermeasure,I need to determine earlier the sequence of activities which would delay the project finish d...

Mar 13, 2014

Progress line on multiple tasks on same line

Forum Topic

Hi,My firm uses a finishes programme for student accomodation, it goes 1st side stud & board, 1st fix M&E, 2nd side board etc. All of these tasks are on one line i.e. room 1. My problem rises when we have for example 90% 1st side board complete but a...

Mar 14, 2014

Progress out of sequence

Forum Topic

Looking for some insight.I have three activities A, B, & C. activity B has started and is 5% complete. Activities A & C have finish to finish logic links to B with a 10 day lag.  Activity B then proceeds to another activity, say D, with a finish to s...

Mar 14, 2014

P6 8.3 webbased data date

Forum Topic

Hi I'm new to scheduling and I had just learned P6 v7 and now am learning v8.3 web.  My original training had me setting the data date for when i wanted an activity of a project to start (this is in a new project that will start in the future) and it...

Mar 14, 2014

Budgeted Man Hour

Forum Topic

Sir, Please help me in the following issue. Already I have a baseline schedule but due to some material delay i had to revise my schedule . As per the new dates already updated the activities but the budgeted manhours was not moving to new dates in a...

Mar 15, 2014

Interactive PMBOK® Glossary Terms and Definitions

Forum Topic

It's FREE!  Within this database you will find all 534 project management terms and definitions located in the Project Management Body Of Knowledge® Glossary (Fifth Edition 2013).  If you are studying for the PMP® exam, you can use this site like fla...

Mar 15, 2014