Progress out of sequence

Looking for some insight.

I have three activities A, B, & C. activity B has started and is 5% complete. Activities A & C have finish to finish logic links to B with a 10 day lag.  Activity B then proceeds to another activity, say D, with a finish to start logic link.  Activities A & C have not started. When I run a schedule update the status indicates that I have progress out of sequence (POS) for activity B.  Activity A & C have important output that must be complete before B can be complete. Why the POS?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts