Search

time-location planning

Forum Topic

hi,is where any other time-location planning sofware other than TILOS (expensive...)thanx

Feb 27, 2012

P6 V7 Export to MSP

Forum Topic

Hello, I tried to export program file from P6 V7 to MSP 2002/2003/2007 in return I got an error code: tbreb 0670-3. While exporting are settings subjected to change? I appreciate a quick solution to my issue. Thanks and Regards, Jesh +971 0551524175 ...

Feb 27, 2012

student needing help

Forum Topic

hi guys, im dong an assignment on asta as part of my degree but im having a bit off trouble working out the best way to do thisthe project is a 3 storey steel frame building and i have to create a program with a max of 140 tasks. my problem is the fa...

Feb 28, 2012

Planning for a LNG Project

Forum Topic

I was assigned to develop and track a LNG project schedule, but i have no experience in this area.Is there anyone experienced in this area. This project is a EPC contract.Can you give me some advice on how to develop this schedule, easy to track it?M...

Feb 28, 2012

Estimation, Rate Analysis, BOQ, DSR,

Forum Topic

 follow this link u get demo for thathttp://bit.ly/HZzSyf Shailesh Sonar’s Estimate.v  Let us learn how to generate Bill of Quantity (BOQ) & Study its Market Rate Justification.v  Abstract sheet is summary of market rate Justification Statement which...

Feb 28, 2012

time-location planning

Forum Topic

hidoes spider has time-location planning functionality like TILOS?thanx

Feb 28, 2012

Are non-work calendar days claimable?

Forum Topic

So, This contractor was working under a 6 day-workweek calendar (Stablished in the contract), but in the seventh day (say, the sunday when there were no one working at the place) a storm hit the place of the works and the 8th day the place was not av...

Feb 28, 2012

P6 saving data confusion

Forum Topic

When you change layout after updating data should you save the layout first. I have noticed when you save layout and then go back into the layout later the data (dates) have changed but if you do not save then the changes are ok. I'm confused because...

Feb 28, 2012

why different values?

Forum Topic

Dear Planners,Plz refer to the picture, my query is, why the value of budgeted hours (in red circle) is different as we multiply the price/unit with budgeted units (showing 8 but actually its 7.5 hours per day calender), as it should be 104x7.5=780 r...

Feb 29, 2012

"peak" function in P6 analytics ?

Forum Topic

hi all,P6 reporting being as good as it is, I'm planning on buying P6 Analytics instead of attempting to re-create the P3 "peak" function in Excel.we currently use P6 v6.2.1, and the resource histogram only shows the "max" resource usage : if you hav...

Feb 29, 2012

Longest Path

Forum Topic

Hi, I'm trying to find longest path activities on my As-Built schedule. But when I filter the activities by using longest path filter I end up with 3 milestone activities. I don't understand why other activities are eliminated by this approach. Pleas...

Feb 29, 2012

Responsibility for concurrent delays

Forum Topic

Say you have two parties, A and B, and the project has totally suffered 100 days of delays. Party A is responsible for 100 days of delays and party B is responsible for 70 days of delay (i.e. 70 days are concurrent delays).   Who is responsible for w...

Mar 1, 2012

MS Project to P6

Forum Topic

Dear All, I need to convert all my programmes in MS Project into P6 version 2. I have done the conversion process as below: 1. Save MS Project as XML 2. Import XML file in P6. I did the steps but it turns out the programme created in p6 does not have...

Mar 1, 2012

filter problem

Forum Topic

I have a resource loaded program which is of 500 activities.1. I want to filter WBS for a single resource but i cannot get the milestones in that WBS which are the responsibility of same resource becoz in P6 we cannot assign resources to a milestones...

Mar 1, 2012

Converting Project Activity Codes to EPS codes

Forum Topic

Hi i have run into a new problem. I created a project with project activity codes(P6.2) . now i want to use the same codes for other projects in the same eps, so i tried to conver them to the EPS codes. As soon as a project activity codes are convert...

Mar 1, 2012