Why when changing a resource does it change the 'Budgeted at completion' to equal the duration?

D
DAVID SMITH 👤 Member for 22 years 2 months

When I manually change a resource, it changes the budgeted units to equal the duration on the activity.

what setting is doing this, i presume it is a tick box somewhere.

Can anyone please help?

Many thanks

Dave

A
Alfredo Jr. Hubilla 👤 Member for 14 years 4 months

Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..

 

Hope this can help.

R
Raymund de Laza 👤 Member for 16 years 6 months

Dave,

Make the Max Units/Time of the resource the same as the previous. 

Hope this will help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts