When I manually change a resource, it changes the budgeted units to equal the duration on the activity.
what setting is doing this, i presume it is a tick box somewhere.
Can anyone please help?
Many thanks
Dave
When I manually change a resource, it changes the budgeted units to equal the duration on the activity.
what setting is doing this, i presume it is a tick box somewhere.
Can anyone please help?
Many thanks
Dave
Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..
Hope this can help.
Dave,
Make the Max Units/Time of the resource the same as the previous.
Hope this will help.