Setup total float relative to sectional milestones instead of project completion date ?

O
Olivia RSA 👤 Member for 14 years 9 months

Hi Guys

 

how do i set this up in primavera, my total float is currently showing relative to project completion date

R
Raymund de Laza 👤 Member for 16 years 6 months

Reece,

Milestone Date of ??? to be linked to last activity within a Section.

Is this milestone is your projected date to complete the section or the entire project?

G
Gary Whitehead 👤 Member for 17 years 2 months

Reece,

Both the solutions in the first two posts will give you what you want.

I strongly advise you setup a dummy project of 6 to 10 activities and trial these solutions thoroughly before applying either. -You need to understand fully the implications before you risk using them on a live project, and your last post suggests you don't understand them very well at the moment.

 

Personally, I would use mandatory constraints rather than lag, as you would have to manually adjust the lag values after each update to maintain the float calculations you want, whereas mandatory constraints will not suffer from this. Mandatory constraints are also easier to toggle on and off, so you can turn them on for reporting purposes, and then take them off again to see the "true" critical path running through your project and actually plan the job properly.

 

Be aware though that both the solutions presented run the risk of generating "false" dates downstream of where you add the lag or constraint. -Which is why it's so important to know what you are doing when you use them.

 

Cheers,

G

O
Olivia RSA 👤 Member for 14 years 9 months

thanx guys but i dont want to show float according to one project completion date

i want to show float according to each sections completion date

 

I searched for long on the net and apparently the only way to do this in P6 is to split the sections up and create mini programs for each section so that primavera sees each section as a program on its own and then calculates the critical path and float for that section on its own, how true is this ?

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

The milestones in every section should be linked with the Project Completion Date milestone and add lags equal to Projected Cpmpletion date - Milestone dates.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts