Hi,
When we split window with Gantt chart on top and resource view below (or vice versa), clicking on the top window causes a filter/shortlist on the below window. Is there any way to stop this?
What I want to do is (for big mpp's), adjust task dependencies and priorities such that that optimal resource allocation for all resources. So what I want is both Gant chart and resource usage in full view i.e. not filter/shortlist views in the bottom view if a row is selected in top view (if you know what I mean).
Is there a way to do this?
regards.
Hi proj2,
no, you can't have a combined view without the top one filtering the bottom one; this is built in MSP
the only way around, but not practical for big mpp's as you say, would be to select ALL the rows in the Gantt Chart; you would see in the bottom pane the project data filtered for ALL the selected rows
Alexandre