why different values?

K
Kashif Khan 👤 Member for 14 years 7 months

Dear Planners,

Plz refer to the picture, my query is, why the value of budgeted hours (in red circle) is different as we multiply the price/unit with budgeted units (showing 8 but actually its 7.5 hours per day calender), as it should be 104x7.5=780 rather than 777

 query.png

Please answer.

regards,

kk

N
Neal Walsh 👤 Member for 18 years 9 months

Kashif,

 

It could be that your decimel settings need reviewing, as it is appears to be rounding up to the near 30mins, similar to what Mike said.

Although by calculation, it comes out at 7.47115 hours!

Other than that, Paul Tobin owes you 52 bucks (technically)   :o)

 

Walshy

G
Gary Whitehead 👤 Member for 17 years 3 months

I believe this value is calculated using the hrs/day factor in Admin preferences menu, not using the activity calendar

M
Mike Testro 👤 Member for 20 years 6 months

Hi Kashif

Probaly because your work pattern is  less than 7.5 but the number has been rounded up in the display.

Check the hours and minutes in your work pattern.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts