Level of effort activity

Dear All ,

 

While loading a cost for my project , i tried to assign the resources for general activities ( e.g. Indirect manpower cost or laydown cost ) to a " Level of effort activity " .

But while updating those LOE activities, i observed that there are no Earned value calculations for those activities .

Is there any way to fix this problem or this is an attribute to LOE activity?

E
Essam Yassin 👤 Member for 12 years 6 months

Well , so how i can assign such reourced ( eg. indirect manpower ) to an activity ??

Z
Zoltan Palffy 👤 Member for 17 years

LOE Activities only measure schedule performance as it relates to time no actual work effort.

Using a LOE to calculate earned value distorts the total project EVM becasue the values derived from LOE grows relative to the total project planned value

LOE does not distinguish cost variance from schedule variance. All variance is recognized as cost variance for LOE work

Featured Partner

Top Posters

Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts