Level of effort activity

Dear All ,

 

While loading a cost for my project , i tried to assign the resources for general activities ( e.g. Indirect manpower cost or laydown cost ) to a " Level of effort activity " .

But while updating those LOE activities, i observed that there are no Earned value calculations for those activities .

Is there any way to fix this problem or this is an attribute to LOE activity?

E
Essam Yassin 👤 Member for 12 years 5 months

Well , so how i can assign such reourced ( eg. indirect manpower ) to an activity ??

Z
Zoltan Palffy 👤 Member for 16 years 11 months

LOE Activities only measure schedule performance as it relates to time no actual work effort.

Using a LOE to calculate earned value distorts the total project EVM becasue the values derived from LOE grows relative to the total project planned value

LOE does not distinguish cost variance from schedule variance. All variance is recognized as cost variance for LOE work

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts