While loading a cost for my project , i tried to assign the resources for general activities ( e.g. Indirect manpower cost or laydown cost ) to a " Level of effort activity " .
But while updating those LOE activities, i observed that there are no Earned value calculations for those activities .
Is there any way to fix this problem or this is an attribute to LOE activity?
you can still put indirect manpower on it
Well , so how i can assign such reourced ( eg. indirect manpower ) to an activity ??
LOE Activities only measure schedule performance as it relates to time no actual work effort.
Using a LOE to calculate earned value distorts the total project EVM becasue the values derived from LOE grows relative to the total project planned value