Primavera can give values of current project planned progress and other on target one ,if we make target plan in such a way that the oll ather things remain same expect planned resources than we can enter actual value in the target plan ,
Be carful in updating the target and donot update resources , this method can give
Actually i want the report on primavera outlook format,i can generate report in excel but it looks fabricated ,Primavera reports give look a system generated report and people believe that it has not been fabricated (although it can be fabricated even in oulook form)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I did not get the answer from any one
but
i thought of one answer
Primavera can give values of current project planned progress and other on target one ,if we make target plan in such a way that the oll ather things remain same expect planned resources than we can enter actual value in the target plan ,
Be carful in updating the target and donot update resources , this method can give
planned histogram
actual target histogram
Hope you have pick it
Regards
Umer
Umar,
Did U get the solution for the above question..?
If yes plz forward me to [email protected]
Regards
Maask
Thank for Reply
Actually i want the report on primavera outlook format,i can generate report in excel but it looks fabricated ,Primavera reports give look a system generated report and people believe that it has not been fabricated (although it can be fabricated even in oulook form)
thanks for replying
Dear Umer,
You can get the planned manpower from resource loading. The actual manpower can be tracked daily based on site reports.