I do have a problem with the Performance % complete in P6 which are not being rolled-up.
Non of the above solutions worked for me. Still in the summary I'm getting zero percent while all of the child activities have been completed and actualized.
Can you explain how to measure the planned % of completion(for the purpose to make the project progress planned curve) in diffrent analysis date from the baseline programme byprimavera 6
Remember there is a switch at the project level in the "calculations" tab, where you can assign all uncosted resources at £1.00. This is good practice if you do not use P6 for resource costing...
Very well done David, I forgot that Id also experienced the same issue due to a lack of $/unit associated with the resources. Pretty certain that the same issue applies when trying to view the resource usage on the web application
The answer is (expert here) that performance % complete is based on money NOT manhours. So all of your resources need costed. If you price them at £1.00 then performance % complete is the Manhour liquidation.
In addition by default primavera does NOT recalculate assignment costs when scheduling by default (you need this) so either recalculate assignment costs under the "tools" pull down, or switch it on under scheduling options (recommended)
If you have added/deleted activities since creating the baseline, you will get the problem of performance & schedule % complete not rolling up. I would suggest updating the baseline to capture any new activities/deleted activities.
You should check the technique for computing performance percent complete set in the earned value tab of your WBS settings, it should be Performance % complete based on activity % complete
% complete should roll up the in the performance % complete column (But not Activity % complete)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi,
I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band
You can find out How Schedule % complete and Performance % complete are calculated in Summary band.
Kindly read it here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/
Payam and Jose you have to have resources you need a measuring stick
Hi guys,
I do have a problem with the Performance % complete in P6 which are not being rolled-up.
Non of the above solutions worked for me. Still in the summary I'm getting zero percent while all of the child activities have been completed and actualized.
Can anyone please help me with this issue?
Cheers,
Payam
Helo all,
Can you explain how to measure the planned % of completion(for the purpose to make the project progress planned curve) in diffrent analysis date from the baseline programme byprimavera 6
Regards,
Joseprakash
Hi folks,
I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.
I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:
Calculations Tab: $1
WBS: Activity Percent Complete
Advance Scheduling: enabled recalculate assignment
Group & Sort: show total
Any help would be very much appreciated.
thanks.
Don
Thanx Mark again & again
regards
Bugger...

This is my last attempt at getting in a link:
Primavera
This should do it for you
Dear David,
May you explain more.
Thx
riad
Riad,
Remember there is a switch at the project level in the "calculations" tab, where you can assign all uncosted resources at £1.00. This is good practice if you do not use P6 for resource costing...
Hi to David,
Thaaaaaaaaaaaaaaaaax David it is done, Thanks to Mark TOO
best regards
riad
Very well done David, I forgot that Id also experienced the same issue due to a lack of $/unit associated with the resources. Pretty certain that the same issue applies when trying to view the resource usage on the web application
Mark
The answer is (expert here) that performance % complete is based on money NOT manhours. So all of your resources need costed. If you price them at £1.00 then performance % complete is the Manhour liquidation.
In addition by default primavera does NOT recalculate assignment costs when scheduling by default (you need this) so either recalculate assignment costs under the "tools" pull down, or switch it on under scheduling options (recommended)
Hi Mark,
Thx for ur Reply, I will try ur comments, I will let U know the result soon.
Thx again.
Riad
Riad
If you have added/deleted activities since creating the baseline, you will get the problem of performance & schedule % complete not rolling up. I would suggest updating the baseline to capture any new activities/deleted activities.
Regards
Mark
You should check the technique for computing performance percent complete set in the earned value tab of your WBS settings, it should be Performance % complete based on activity % complete
% complete should roll up the in the performance % complete column (But not Activity % complete)
Experts, now 17 Viewers, No Answer!
Kindly do Help me.
THX