Schedule & Perforemanc % Complete Roll up

P
Payam Rezaeian 👤 Member for 8 years 10 months

Hi guys,

 

I do have a problem with the Performance % complete in P6 which are not being rolled-up.

Non of the above solutions worked for me. Still in the summary I'm getting zero percent while all of the child activities have been completed and actualized. 

Can anyone please help me with this issue?

 

Cheers,

Payam

J
Jose Prakash 👤 Member for 14 years 11 months

Helo all,

Can you explain how to measure the planned % of completion(for the purpose to make the project progress planned curve) in diffrent analysis date from the baseline programme byprimavera 6

Regards,

Joseprakash

D
Don Villaflor 👤 Member for 15 years 1 month

Hi folks,

I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.

I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:

Calculations Tab: $1

WBS: Activity Percent Complete

Advance Scheduling: enabled recalculate assignment

Group & Sort: show total

Any help would be very much appreciated.

thanks.

Don

 

 

 

 

D
David Kelly 👤 Member for 21 years 9 months

Riad,



Remember there is a switch at the project level in the "calculations" tab, where you can assign all uncosted resources at £1.00. This is good practice if you do not use P6 for resource costing...

R
Riyadh Yahia 👤 Member for 18 years

Hi to David,



Thaaaaaaaaaaaaaaaaax David it is done, Thanks to Mark TOO



best regards



riad

M
Mark Porter 👤 Member for 18 years 11 months

Very well done David, I forgot that I’d also experienced the same issue due to a lack of $/unit associated with the resources. Pretty certain that the same issue applies when trying to view the resource usage on the web application

Mark

D
David Kelly 👤 Member for 21 years 9 months

The answer is (expert here) that performance % complete is based on money NOT manhours. So all of your resources need costed. If you price them at £1.00 then performance % complete is the Manhour liquidation.



In addition by default primavera does NOT recalculate assignment costs when scheduling by default (you need this) so either recalculate assignment costs under the "tools" pull down, or switch it on under scheduling options (recommended)


R
Riyadh Yahia 👤 Member for 18 years

Hi Mark,



Thx for ur Reply, I will try ur comments, I will let U know the result soon.



Thx again.



Riad

M
Mark M 👤 Member for 18 years 1 month

Riad



If you have added/deleted activities since creating the baseline, you will get the problem of performance & schedule % complete not rolling up. I would suggest updating the baseline to capture any new activities/deleted activities.



Regards

Mark

M
Mark Porter 👤 Member for 18 years 11 months

You should check the technique for computing performance percent complete set in the earned value tab of your WBS settings, it should be Performance % complete based on activity % complete



% complete should roll up the in the performance % complete column (But not Activity % complete)

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts