No

Progress out of sequence

Looking for some insight.

I have three activities A, B, & C. activity B has started and is 5% complete. Activities A & C have finish to finish logic links to B with a 10 day lag.  Activity B then proceeds to another activity, say D, with a finish to start logic link.  Activities A & C have not started. When I run a schedule update the status indicates that I have progress out of sequence (POS) for activity B.  Activity A & C have important output that must be complete before B can be complete. Why the POS?

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

"critical path" early warning , Total float

Hi folks,

Critical path is the sequences of activities which their Total float is 0. When this sequence is defined, it is already late to take countermeasure,

I need to determine earlier the sequence of activities which would delay the project finish date.

Should I fix a threshold of the total float? How would this sequence be called? , sub critical path , near critical path ?...

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

A Pipeline Project

N
Nithin Raju 👤 Member for 12 years 3 months

Hi,

I am a new member of this forum and new to process engineering field. I would like to seek your valued help regarding a project I am currently working on. I would like to know how I can plan and schedule a pipeline replacement project. Any help (WBS, suggestions, points to consider) is appreciated. 

Thank you

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

stacked histogram

Hello guys, 

 

I have loaded the manhrs in p6 to my project. The problem which i am facing is my stacked histogram graph peaks does not match my resource histogram peaks.

As i sant to have my histogram trade wise.. and its getting complicated .

 

please help.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Resource histogram

Hello Experts I am struggling with the below scenario and hope one of you can help me out.

I have some plans working on a 7day 7 hour calendar.  If I have a task which only takes 2 hours to do and lets say 3 men to do it, I want to be able to show in my histogram that I want 3 people of a particular trade that day.

I am trying to either use Primavera to show the results or by exporting them to Excel but the results I am getting only show that I want 1 person because it equates a full day to 7 hours and knows I need to get 6 hours of work done. 

 

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Dissertation Questionnaire - BIM & health and safety

J
john khoza 👤 Member for 12 years 3 months

I am a student at Oxford Brookes, studying Project Management.



The aim of this study is investigate building information modelling, to gain an understanding of its success in terms of programming & 4D - Visualisation. To assess how that relates to health and safety on site, with particular focus on in the U.K construction industry. In order to achieve this aim, the following objectives have been established.



1.How does building information modelling perform in terms of programming & visualisation?

2.How does that relate to safety on site?

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts