Total Float

R
Raza Raza 👤 Member for 12 years 3 months

Dear All, 

 

I have received a shcedule from Contractor for review with activties having very high float like 260 days, 120 etc........same like free flaot is very high. Its 16 months project .

 

Is there any standard practice limit  for activities could assign free float, total float or lag in schedule.

 

Also if I am reducing the duration of critical activties the mechanical completion date is going beyond the project mechanical completion date despit it shall be completed before,.....

 

 

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Late Start and Late Finish earlier than Early Start and Early Finish

Dear all,

In a schedule that I used the same calendar for all the activities I experienced the fact that for some activities on critical path the late dates were earlier than the early dates.

e.g. ES:1-MAR-2014 LS:28-FEB-2014 late start one day before the early start, while what I expected was to happen the same day 1MAR2014.

 

Any ideas?

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

where to find labour or machine constant values online

S
shang gao 👤 Member for 12 years 3 months

Hi all, 

can anyone please advise where to find labour or machine constant values online?

it there any free sources such as Rawlinsons construction handbook online.

If not, how can you get the labour or machine constant values to estimate the activity duration when the BoQ is ready.

 

Cheers,

Gao

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Unassigned baseline problem with current project

Hi All,

Although i havent assigned any baseline to my schedule in bar chart i see baseline bars(project,primary or secondary) for actual activities seen attached picture

When i assign baseline i also see same bars

Can anybody help me?

Kursat[[wysiwyg_imageupload::]]

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Local/Govt Regulation requirements(work permits) for Malaysia

K
kumar s 👤 Member for 16 years 5 months

Dear All,

 

I am presetly preparing Level 3 schedule for a EPC Project in Malaysia.I have to add the Local/Govt regulations and work permits required in to the schedule.As of now,I have only around 10 work permits listed in the schedule,which is very high level.

Does anyone know the detail work permit requiement and the sequence to be followed in the schedule preparation.

 

Thanks,

 

Kumar s

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Adtivity Duration and resource levelling

N
Nikan G 👤 Member for 12 years 5 months

hi people,

I am new in planning, and It would be highly appreciated to answer my BASIC questions :)

  • Have an activity which actually takes 12 hours but in 2 weeks, how I can plan it? already in my schedule,  it started on 17th Feb and will finish 28th Feb., which is 80 hours for duration that is not correct, what is planning solution for this?
  • the resource who is working on above job, is working on other four tasks as well.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts