Time Impact Analysis for Weather Delay
Hello,
I have an in-progress activity that was delayed one day by bad weather.
The Owner agrees that the weather stopped work and wants a Time Impact Analysis with a fragnet added that shows the forecast completion date pushed out by one day.
Do I break the activity in two and put a single weather day activity in the middle of the two activities?
Do I add the weather day with a FF relationship with the activity?
Note that the schedule is setup where inclement weather was accounted for in the calendars, not as an activity at the end of the schedule.
Thanks!