Event Code CCF"C-2994-C

While importing an Excel file an event code was displayed (CCF"C-2994-C) and I was unable to complete the import.

 

Please help me out.

 

Regards

Bilal

Z
Zoltan Palffy 👤 Member for 16 years 10 months

 if the path begins with the C:\ drive, the error will display CCF"C-xxxx-x

it appears that you do not have access to that excel file try saving it to another location and try the import again.