Change Duration when adding extra Resource
Hi All,
What settings must I use to get P6 to change Activity Duration when I add extra Resources?
Lets say I have I have a 10 day activity with 1 Resource on it and 100 units, when I add an additional same Resource I want the duration to reduce to 5 days and retaining 100 units.
Thanks,
Rod