Loaded my permitting with units to track an s-curve. Assigned 200 000 units across the activities. My report only has 194104 units in cumulative planned but cumulative estimate to & at completion indicates the 200 000 units loaded. No filters assigned that can trip me up and percent complete type set to units.
What could be the problem?
Running 18.8
under edit user preference
turn your decimal places on
Time units tab
Thanks David, found it is exactly the problem.
Going to delete resources and reload as I guess this is the only fix.
Primavera holds the numbers in two places, and they do get out of synchronisation.
You should check the units in both the “Activities” window and the “Resource assignment” windows
When you do a resource profile/spreadsheet, the numbers come from one table, the Activity spreadsheet/profile and ALL earned value data comes from the other.
make sure your filter is set to ALL activities