Oracle Primavera - PM6

Description

Here's a place to discuss some Primavera Enterprise questions

Container
No

Work Completed or progressed in the last reporting period

R
Ron Beechey 👤 Member for 10 years 2 months

Is there a method to capture and report the work that had been progressed or completed in the last reporting period.   Using a filter i created finish date is in the range of DD-7days to DD which will show all work completed.   But some of the tasks are progressed by say 25%.   Could I get that from the Baseline which I update each week.  But how?

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Planned Start / Planned Finish dates in relation to cost loaded spread of monies

Good Afternoon,

I have re-visited some cost loading bars in the programme and split them out in order for the commerical team to accurately represent the cost spread.

The actual start date for the cost bars is in the past, i.e. before the data date and have been actualised. Whilst reviewing the spread of the budgeted cost, it was clear the monies were not being spread across the correct months. To try and rectify this, I deleted the resource and assigned a completely new resourse budget and put it on a linear curve. This did not work.

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

P6 v 8.2 not installing

Using the agents laptop with v 8.2 for several months now and today it would not start.

The error message says Primavera P6 Professional R8.2 has stopped working.

A problem caused the program to stop working correctly. Windows will close the program and notify you if a solution available.

The debug option also thows up an error when run.

Anything I can do about this?

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Primavera P6 Professional v18.8 Importing XML files failing

Hello,

I recently upgraded to Oracle Primavera Professional version 18.8 and now I am unable to import P6 XML files or Microsoft Project XML files. This happens for both a MSSQL database and SQLite database.

Also, I went to the Oracle website https://edelivery.oracle.com. The latest version of P6 Professional was 18.8 and I did not see a patch fix later than 18.8.0.0.

Any input or guidance would be greatly appreciated.

--Steve

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

BL Budget At Completion and PV is Not Matching At Completion Total Cost for a Completed Activity

Hi,

capture.jpg

I have an activity in my schedule that has a Budget At Completion=PV=EV=$16,451.87, while my At Completion Total Cost for that activity= $66,084.98 (as in the attached screenshot).

The Baseline was snapped two months after the activity finish date was actualized; I tried to update the BL couple of times for that specific activity, but its still showing No matching values. 

Anyone went through this situation before please?

Thanks.

 

Ali

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

How to indicate Physical percent completed in Group bar

V
Viet Tran 👤 Member for 9 years 3 months

Hi everyone,

In my turnaround project, I chose the percent completed type is physical percent completed, but the problem I faced was that percent can not show at WBS or total bar as well. Can you advise me how slove this problem?

Thanks alot.

Viet Tran.

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts

Primavera P6 Professional v18.8 XML file import fails

Hello,

I have a Windows 10 computer. I recently updated Primavera P6 Professional to verion 18.8. Unfortunately, now my XML file imports fail everytime I try to import a P6 XML file or a MSP XML file. Imports fail for both a standalone MSSQL database and a SQLite database.

An example log file from a failed P6 XML import is below.

Any input?

______________________________________________

Forum Sponsor

Top Posters

Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts