Hi everyone,
In my turnaround project, I chose the percent completed type is physical percent completed, but the problem I faced was that percent can not show at WBS or total bar as well. Can you advise me how slove this problem?
Thanks alot.
Viet Tran.
I expect turnaround projects to be scheduled using multiple shifts; my emphasis would be to keep a good model that can consider multiple shifts on same activity. Splitting the activity into multiple ones would add chaos on turnaround projects where updating must be frequent and there is no time for guessing how work is to be re-distributed among different shifts on same activity.
Because turnaround projects move so fast, things might change fast. We need to capture the changes ASAP and make adjustments in our coordination to get right people and materials in place at the right time. There is not much time to make manual adjustments; we need to get it right and fast.
If you want to add more into the mixture of %Complete definitions you might define %Duration Complete as [Actual Duration/Baseline_Cumulative_Duration] X100.
Old P3 would allow you to define Cost%Complete as wll as Effort%Complete based on either current schedule or one of two comparison baselines and show these values on the S-Curves instead of the numeric values. This might allow for %Complete be over 100%. Please take a look at the following figure.
I have a preference on using values where there is no room for confusion or ambiguity.
With numeric values along with some unit of measure you get more complete and meaningful information, it is better than some ratio; to say 100$ out of 300$ or 30$ out of 90$ gives you more information than to say 33%. If someone is interested in in whatever definition of %Complete to use then with Excel any ratio or % as well as the corresponding %S-Curves can be generated.
in the gantt araea right click and select bars on the left hand side look fo the Name entitled current bar label
then select the Bar Labels Tab and at the bottom select add and then select the position of where you want your percent shown then under the label select any type of percent that you want to show.
The following might also be of interest:
I suggest you use the Duration % for turnaround project.
There is not a single number that will tell you all. I would suggest tracking project duration and effort. Tracking many other parameters might be too much for turnaround projects .
Unfortunately P6 %Duration is counter-intuitive and can be misleading.
https://www.planacademy.com/primavera-p6-duration-percent-complete-guide/
I use different software. Take a look at the following figure %Duration and %Effort are different. If at gunpoint asked to select a single %Complete figure I would pick Intuitive %Duration for turnaround projects where main focus is on project duration.
With old software such as Primavera SureTrak %Complete was related to duration, unfortunately formula and roll up was not intuitive. This I see as a reminder of how important time element is in scheduling, as our contracts say "time is of the essence".
Thanks Refael and Raymund for your respond,
Agree with you that Physical percent is separated between remaining duration and physical work achieved, so It does not "roll up" or summarize at the WBS level.
But as you know, when the manager looks at the schedule, they shall first look at the actual percent and plan percent to see the deviation, and the detail maybe later. So, ok, I will try with Performance % compelete as mentioned by Raymund.
@By the way, can you advise me how the choose the correct percent complete for Turnaround schedule?
Many thanks,
Rolling-up Physical % Complete only makes sense for common parameters.
Viet,
Roll up Sum will be shown in the Performance % Complete Column if the Schedule is Cost Loaded.
Hope this will help.