I would like to group my layout on a given level of the wbs and below
So I would like to select level 6 and below and not show the upper levels (1-5). Is there a method by filtering or selecting that I have missed
I would like to group my layout on a given level of the wbs and below
So I would like to select level 6 and below and not show the upper levels (1-5). Is there a method by filtering or selecting that I have missed
I have found the method to work with the WBS. In the grouping window select WBS and then turn off Indent and select the level to start on. If you need a second level add WBS again and select the next level to add to the grouping.
We created a wbs what made it down to the system level and then the piping line level. These are the ones I would like to see the tasks grouped and sorted by.
This could be good info for all users.