P6 EPPM v20.12 LOE actual labor units not populating
Hello,
My project management level of effort (LOE) activity has progressed Duration % Complete 7.89%, but the actual labor units of the assigned labor resource is not populating. I tried the below:
1) Actions | Recalculate assignment costs.
2) Schedule option 'Recalculate assignment costs after scheduling' set to on.
3) Percent Complete Type of LOE project management activity set to Duration.
4) Set 'Recalculate actual units and cost when Duration % Complete changes' set to on.
5) Duration type set to 'Fixed Duration and Units'.