Hi P6 experts, I am looking at Duration % Complete column and noticed that the activity with lowest Duration % Complete, its Duration % shows at the WBS level. It seems that at WBS level, the software isn't calculating the correct Duration % Complete, rather just showing Duration % of the activity that has lowest Duration % value Can someone advise on how to get correct Duration % value at the WBS level? Thanks
Incorrect Duration % Complete value at WBS level
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
glad I could help
Thanks Zoltan!
Duration % Complete = percent complete of the activity duration.
Formula = (Original Duration - Remaining Duration)/Original Duration * 100.
Note: Original Duration is taken from the current plan, not from the baseline.
That is correct.
However
The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far
Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.