Hi Planners
I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.
Regards,
Muataz
in the general tab is the % complete type set to physical
did you check the Started box next to the date ?