Hi All,
I have a schdule which is resource and cost loaded (By unit rate of Resouce), which is the baseline.
After a week I scheduled it.
So in the WBS how can I see what was the Baseline Planned % til date for Progress and Cost
And what is the actual % complete for progress and Cost on that scheduled daat date?
What coloumns represents that?
Warm Regards
Jtihin
Hi Jithin,
Assuming that you have all the settings in place and correct such as maintain and assigned baseline to current project and it was match on the project settings on baseline for earned value calculation, Earned Value calculation was set on Budgeted Value with Planned Date, checked and recalculate cost and total Budget At Completion is correct then the following should have the correct data:
Column to show:
Hi Jithin,
Try these columns to show Planned Values (PV) and Earned Values (EV).
When you say Actual % do you mean the actual cost (such as operating costs, material costs, overheads) that is keyed in by the user, or do you mean the Earned Value, which is auto-calculated by P6 based on the % complete of the activities keyed in by the user