Drawbacks
Pls list out the drawbacks of Primavera. ( eg resource assignment can be done automatically depend on the resource availability)
- Read more about Drawbacks
- 2 comments
- Log in or register to post comments
Here's a place to discuss some Primavera Enterprise questions
Pls list out the drawbacks of Primavera. ( eg resource assignment can be done automatically depend on the resource availability)
is there a shortcut to assign multiple new activities i created to a wbs all at once? one by one is taking too much time
My project has only two main wbs, building and sitework
i first created building wbs and the wbs under it
then i created site
but now it shows site on top of building wbs. both in wbs view or the activity view. how can i bring sitework to below buuilding wbs?
Here's a great tip on how to transfer filters in Primavera P6 Professional http://ow.ly/bMPE309VAQE
Hi,
I have a question, please help me.
I revised durations in a schedule at P6 regardless of remaining units and remaining duration and submitted to HOD.
The original budget available and duration type already defined by previous planner is fixed duration & units.
The client asked to revise the budget and add the revised budget in P6 and then from P6 take the weekly planned budget.
How can I revise the budget unit without changing the duration and date?
Hi
Need your support here.
This is related to Manufacturing planning works.
Activity A (Machining operation) - 15 days
Activity B (Machining operation) - 10 days
Activity C (Machining operation) - 20 days
Activity D (Machining operation) - 25 days
Activity E (Machining operation) - 5 days
Activity F (Machining operation) - 5 days.
Hi
Whether automatic resource assignment based on activity operation is possible in Primavera to get better result.
Since we are consuming time while preparing the manufacturing shedule which will consists of many similar operations.
Any suggest / help.
Regards
Ram
I've been using Primavera P6 for a few months now and I notice that the time of finish for different ativities turns out to be different even when I check them all off as complete at the same time. Is there some setting with respect to time that I'm missing somwehere?
For Example, if I used a data date of March 8 and checked off complete for two different activitie before I scheduled, one would show completed at 6.00PM and the other would say 4.00PM. I've seen multiple timings like this.
Suggestions would be greatly appreciated.
Hi,
Does anyone know of any tools on the market that interface with Primavera P6 to support multi project critical chain implementation?
Thanks
What if you want to delay the start of one resource working on an activity? Yes, it is possible in Primavera P6 Professional to add lag on a resource. Here's how http://ow.ly/nzwu309MjEl