Previous Month Status File Shows Incorrect Actuals

S
sam dsoza 👤 Member for 20 years

Hi

I have a P6 Master Forecast File. I have attached the Baseline File (BL) and Last Month Status File (BL1).

When I compare dates shown in Last month P6 file the dates do not tie to the actual dates for activities concerned. I am stumped as to why I see incorrect actual dates in the previous month file. 

Has anybody else encounteres this problem and what is it that I am missing or doing incorrectly?

 TIA

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Remaining Total Cost Distribution

Hello everyone,

I have an activitiy (not started) which is scheduled to start in 29 March 2017 and finish in 08 May 2017. However, when i chect the remaining total cost layout, it shows the total cost only in May 2017. It does not distribute the cost evenly.

I do not have any curve assingned to that resource. 

Calculation settings which are checked:

Link budget and At Completion for not started activities

Reset remaining duration and units to original

Substract actual from at completion

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Event in Aberdeen

D
David Kelly 👤 Member for 21 years 8 months

PMI Aberdeen - Tuesday 14th March 18:30hrs

Summary:

After Forty years implementing computerised Project Controls, why is everything still the same?

Nearing the end of his career, David muses on a lifetime of trying to help people manage projects better. From mainframe to iPhone, the float is still negative. Has any of it helped? 

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Saving Different Language in P6

R
Ron Liu 👤 Member for 9 years 4 months

Hello everyone,

I have problem saving P6 acitivities that are entered in a different language. I'm using P6 16.1 and my activity description is in Japanese. When I'm done entering the activities and exist the schedule, all activities would display question marks when I open the schedule again.

Does anyone know a fix?

Thank you.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Stacked Histogram across suite of Projects sorted by Role

I have a suite of projects that is resource loaded with defined roles first and people filled in as resources once they are assigned.  I have a stacked histogram set up to show by resource and by role separately. Is there a way to combine that function in p6? I need to be able to choose a role and show that stacked histogram for say "engineers" and have the stack be bob, suzy, joe, fred, etc., excluding "project managers" and "designers", for instance.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts