Resource Budgeted Units change?

This is more than likely a simple answer....

Example:

10 day activity for an electrical resource. 4 guys needed on the job for days 1-6, then drop to 2 guys for days 7 & 8 and back up to 4 for days 9 & 10.

Can this be achieved in a single activity, or do I need 3 separate activites linked F-S and up/down the resource as required?

 

Cheers,

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

activity complete and Schedule % complete not maching

Hi Friends,

I have an LOE activity with SS and FF relationship to a set of activities.

There were delays in the activities and the orignal and at completion is now different for the activities as well as the LOE activity now.

The activity % complete is less that Scheduel % complete which is exptected.

But now the current dates have been accepted as new baseline. But even if I save the current project as the baseline, the activity % complete and Schedule % complete are showing different value, for LOE as well as its predecssor activities. Can I fix it?

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Recommended way to update the progress in P6

C
Chary Chary 👤 Member for 10 years 2 months

Dear all,

I am new to Primavera. With all the manuals I am sort of still lost on what is the meant procedure to update status / progress of activities in Primavera and you can change several things and the tool will re-calculate the other (e.g. updating duration % complete will update remaining duration)

Is my understanding correct, that procedure looks like this

Step 1

Think of Data Date for which you are updating progress

Step 2

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

P6 comparing roles budgeted units with units of resources available

G
Gema Arenas 👤 Member for 9 years 8 months

Good afternoon,

I am trying to find a way where I can assign roles to all the activities in my different projects and do a comparison or perform a gap analysis of the resources available for each role.

The idea is that we can have a look ahead of which week we will be low on resources in comparison to the roles you have budgeted for.

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

CAN I FACE (1Z0-567) Primavera P6 EPPM 8 Certified Implementation Specialist with out OPN

Dear all,

i am currently employed in compnay which doesnt holds a  OPN(Oracel Partners Network), but i am keenly interested in facing this exam and improve my employability and skill set as planner 

 

please do recommend

thanks in advnace 

regards shujath  

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

CAN I FACE (1Z0-567) Primavera P6 Enterprise Project Portfolio Management 8 Certified Implementation Specialist

Dear all,

i am currently employed in compnay which doesnt holds a  OPN(Oracel Partners Network), but i am keenly interested in facing this exam and improve my employability and skill set as planner 

 

please do recommend

thanks in advnace 

regards shujath  

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Saving different versions of a project

A
Ahmet Tuter 👤 Member for 13 years 4 months

I will save a copy of my project once i complete all durations and links, but before assigning any resources and calendar, even before creating those.

then after saving it, i will continue and create resources and calendar, then assign reosurces and calendar in to the second version.

now, if i were to open the first version again, for any reason, would all those resources and calendar, that i did after it, be available to it also?

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts