how to asign multiple activities to a wbs?

A
Ahmet Tuter 👤 Member for 13 years 4 months

is there a shortcut to assign multiple new activities i created to a wbs all at once? one by one is taking too much time

Z
Zoltan Palffy 👤 Member for 16 years 11 months

2 options

option #1

if you can get your activities lined up or group another way then you can add a column for the wbs and then do the 1st one and then do a fill down

option #2

you can export the activites to excel when you export them if they have not been assigned they wil automatically  take the wbs of the project id that is the highest level. You can then change them in excel and import them back into p6

Z
Zahid Rehman 👤 Member for 15 years 2 months

I was looking for the solution of the same issue since last one week but in vain.... Thanks Chandran , this tip really worked...

R
Rama Chandran 👤 Member for 14 years 5 months

Select the activities (Ctrl+Activity).

Move the cursor to the left side of the activity table. Cursor with small rectangle appears.

Now drag the activities to the needed WBS.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts