primavera

Quick Update - a process that explains how to update Primavera schedules in quick time

Full Article / Information

"Quick Update" is a process that explains how to update Primavera schedules in quick time.

This presentation will illustrate how to update a schedule in 8 short stages.

  1. Create a Baseline
  2. Switch ON auto schedule
  3. Ensure that Baseline Bar is switched ON
  4. Apply Actuals
  5. Move Data Date Forward
  6. Review IN PROGRESS activities - Update Remaining Duration/Finish Dates
  7.  Review progress of activities on Data Date - Update Start Dates
  8. Switch OFF auto schedule

Author:- David R.V.Forrest

Use of Constraints in P6–A Guidance Note

Full Article / Information

The purpose of this document is to provide general guidance to be followed when using constraints in P6 schedules, or approving P6 schedules on behalf of clients. The guidance covers the effect of each constraint type on the schedule, plus advice for appropriate use. It is written based on P6 constraints and terminology, but similar principals will apply across other software packages.

Calendar for scheduling relationship lags

P
PP Admin 👤 Member for 17 years 4 months

QUESTION

Dear Mr P6 Civils,

When running our calculations in P6 8.2, we noticed that under schedule options, the calendar for scheduling relationship lags was set to Successor Activity Calendar.  I assumed is should be scheduling off of Predecessor Activity Calendar. Is the default Successor Activity calendar? If so why? I would assume you want to base your lags off the predecessor activity. This will affect your schedule especially if you are using different calendars.

Promotion of activity codes in Oracle Primavera P6

P
PP Admin 👤 Member for 17 years 4 months

QUESTION

Dear Mr P6 Civils,

I know you can promote activity codes in P6.  What I want to know can you promote project codes to EPS codes and EPS codes to Global Codes or is it just promoting project codes to Global Codes.  I have promoted codes before I just cannot remember if there is a hierarchy of the codes or not.

Regards…

SUGGESTED ANSWER

Activity Codes in Primavera P6 can be created at three different levels.

·         Project level Activity Codes