Primavera Tips and Tricks - Tracing logic to a targeted activity using Primavera P6

Primavera Tips and Tricks

Tracing logic to a targeted activity using Primavera P6

Project Controls – Planning and Scheduling

July 2018 By David H. Doughty, PSP

Introduction:

In this post, I will show you how trace logic to a targeted activity on your project by utilizing Multiple Float Path functionality in Primavera P6.

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture: