Bid/Project Planning Engineer, BK Gulf, Dubai International Airport Expansion Project Phase – II

P
Prem Ananth 👤 Member for 12 years 11 months
START Date
  • Develop realistic programs up to Work Breakdown Structure level IV
  • Produce Master procurement schedule / drawing schedules / Material submittal registers / Work inspection registers
  • Resource / Cost loading & Tracking
  • Leveling resources to achieve maximize productivity
  • Develop Manpower Histogram and resources forecast curves.
  • Knowledge in FIDIC clauses
  • Able to handle Civil / Fit-out Works
  • Track and report progress achieved on bi-weekly / monthly basis
  • Attend Progress review meetings with client / consultant
  • Load Quantities and monitor Key Project Indicators (KPI’s)
  • Report access / construction delay’s