- Preparation of contractual programs – Clause 14.1 for the awarded projects, in co-ordination with the project manager of that respective project, and assigning the quantities and manpower in the program for following up during updating, time wise and quantity wise.
- Preparing the Internal Target program, for the internal use of Al Habtoor Company, with same starting date and 2 month or less from the Clause 14.1 finish date.
- Updating the Clause 14.1 & Target Programs of nearly 4000 activities.
- Recovery Programs.
- Preparing Weekly & Monthly progress program (time & quantity wise) showing the actual situation delay/ahead comparing to the target, early and late start clause 14.1 programs, in addition to actual manpower used comparing to the planned.
- Preparing 1-month ahead program for the activities to be executed the next month.
- Forecast weekly and monthly reports to catch up the target/Clause 14.1 programs(incase of delays)
- Preparing the report for the co-ordination meeting monthly.
- Following up all the site activities on site, including approvals, subcontractors and material approvals, structural and finishing activities.
- Attending progress meetings with Client, Project Managers, Consultant, Project Director and Sub contractors.