Al Habtoor Engineering Enterprises
Al Habtoor Engineering Enterprises
Manjunath rn
MD.MOSTAFIZUR RAHMAN
Lead/Senior Planning Engineer, Al Habtoor Engineering Enterprises, 170 Public Villas at Al Samha, Al Raha Beach Resort (5 Star Hotel & Shopping Mall, Dubai Marina Terrace – A 38 Storied Tower)
- Anchored on-site construction activities to ensure completion of project within the time & cost parameters.
Engineer, Al Habtoor Engineering Enterprises, Dubai International Airport Expansion Phase 2
I was part of the amazing team building the Dubai International Airport expansion Phase II (Contract AX059). It was a great experience and I have learned a lot from this job.
Construction Project Planner / Senior Planner, Al Habtoor Engineering Enterprises, Burj Al Arab, Carlton Hotel, Holiday Inn Hotel, Marina Mall
Senior Planning & Controls Engineer for a reputed Contracting Company - AL Habtoor Engineering wherein I was involved in Planning of world famous structures like Burj Al Arab which is a 7 star hotel and Marina Mall which is a modern shopping complex with more than a million square feet retail space.Also involved in Planning, monitoring and control of 30+ stories towers for Holiday In Hotel.
Heading a team of 4 planners and responsible for development of Baseline schedules, montoring and reporting.
Project Planning Engineer, Al Habtoor Engineering Enterprises, Jumeirah Beach Residence S4, Al Sofouh Tower, Movenpick Hotel
Please be informed Planning Planet Account ID 2669 to be updated. Thank you.
email : [email protected]

Reynaldo Y. Calayo Jr.
Project Planning Engineer, Al Habtoor Engineering Enterprises, Construction of Business Bay Sales Centre, Construction of 12 Towers @ Business Bay and Construction of Commercial Tower @ Dubai Marina, Dubai,
- Preparation of contractual programs – Clause 14.1 for the awarded projects, in co-ordination with the project manager of that respective project, and assigning the quantities and manpower in the program for following up during updating, time wise and quantity wise.
- Preparing the Internal Target program, for the internal use of Al Habtoor Company, with same starting date and 2 month or less from the Clause 14.1 finish date.
- Updating the Clause 14.1 & Target Programs of nearly 4000 activities.
- Recovery Programs.
- Preparing Weekly & Monthly