Senior Planner, Bateman Africa, Kusile Coal Fired Power Station – South Africa

START Date

Employed as Lead EPC Planner overseeing three major packages (projects) on the Eskom Kusile Power Station. (LSTK Project)

Implementing project control system, including POP (Procurement Operating Plan) & EOP (Expediting Operating Plan).

Developing the EPC Schedule to provide an object orientated WBS, on a fully resource and cost loaded schedule. Progress performance and analysis reporting, including, S-curves and progress reports. Supervise, manage & mentor two Planners working under me.

All the normal planning, scheduling and project control requirements needed for managing a mega project.

Currently at end of Eng Design Phase (97, 928 manhours) and going into Construction Phase.