Progress & Performance

Senior Planner, Bateman Africa, Kusile Coal Fired Power Station – South Africa

START Date

Employed as Lead EPC Planner overseeing three major packages (projects) on the Eskom Kusile Power Station. (LSTK Project)

Implementing project control system, including POP (Procurement Operating Plan) & EOP (Expediting Operating Plan).

Developing the EPC Schedule to provide an object orientated WBS, on a fully resource and cost loaded schedule. Progress performance and analysis reporting, including, S-curves and progress reports. Supervise, manage & mentor two Planners working under me.

Senior Project Controls Specialist, Fluor Daniel SA, QMM Ilmenite Mine for Rio Tinto (Fort Dauphin, Madagascar)

START Date
END Date

First based in the Home Office Projects Control environment in Johannesburg, where I developed and maintained the Master Project Schedule, during the engineering & procurement phase of the project.

My responsibilities involved co-ordination with engineering and procurement departments to manage the drawing and equipment delivery interfaces with the schedule.

During the construction phase, I was site based in Madagascar, where I was also the ‘Milemarker’ practitioner (a Fluor system for measuring progress and performance).